How Many PPE Coveralls Can be Made by One Hot Air Seam Sealing Machine?
Body CoverallThe essential operations in a body coveralls making is heat sealing operations of all…
Ergonomic Design of Workplaces in The Apparel Industry
Ergonomics in the apparel industry may seem like a far-fetched word. This is because most…
Difference between Minutes Produced and Minutes Attended
Question: In the Efficiency calculation formula, you have mentioned this - Factory efficiency% = (Total…
These 4 Activities You Can Do While Working from Home
Image Source: https://workful.com/ OCS blog is a knowledge platform for apparel industry professionals and newcomers.…
How to Derive Garment SAM from Production, Efficiency and Manpower Data?
This question was posted on ASK OCS platform by an OCS reader. I have these…
Average Operation Cycle Time – The Key to Labor Costing and Production Scheduling
The average operation cycle time is the key data in labor costing and production scheduling…
How Many Operators Do I Need to Balance a Line (with SMV and Line Target)?
I have the following data of a sewing section. How many operators do I need…
How to Calculate Hourly and Daily Target When Line Works at 45% & 60% Efficiency?
Rajib Asked: Garment SMV=11.25, Number of Worker=25, Hour=10. What would be the hourly and daily…
Key Qualities Needed to Be a Successful IE Manager in Manufacturing Industries
What are the key qualities one needs to be a successful IE manager in the…
How to Calculate Man to Machine Ratio for a Double Shift Plant?
Normally, the man to machine ratio (MMR) is calculated considering a single shift. Though sometimes…